How do you create a data center meter on a data center property use? Follow

Creating a data center meter on a data center property use is a two-step process. First, the meter must be created. The following example creates an IT energy meter (for Data Centers) for a property that has an id of 893.

POST /property/893/meter<meter>

   <type>Power Distribution Unit (PDU) Input Energy</type>

   <name>PDU Meter</name>

   <unitOfMeasure>kWh (thousand Watt-hours)</unitOfMeasure>

   <firstBillDate>2010-01-01</firstBillDate>

   <inUse>true</inUse>

</meter>

Next, the meter must be associated to the property use, using the meterID returned in response to the meter creation POST, as follows:

POST /association/propertyUse/(propertyUseId)/meter/(meterID)

.